TDOT will shut Nashville’s James Robertson bridge from summer 2027 to summer 2029
NASHVILLE — The James Robertson Parkway bridge into downtown is scheduled to close for about two years, starting in the summer of 2027, after the Rock and Roll Marathon, and reopening by the summer of 2029. Erin Zeigler of the Tennessee Department of Transportation told NewsChannel 5 the closure is longer than the department first estimated because crews will put utility lines into the bridge. TDOT wants the work done before the Super Bowl in early 2030. No official detour has been published.
The bridge runs beside the Metro Courthouse. Zeigler said more than a closure is at stake for the East Bank: “We’re going to be lowering the approach to the James Robertson Parkway Bridge, and that is because we are creating a seamless street grid into the East Bank Development.” The elevated concrete over land on the East Bank comes out. The span over the Cumberland River stays. The lowered approach is supposed to meet the ground at what is now South First Street, so a future East Bank Boulevard can cross in front of the new Titans stadium. “We know that any closure of this bridge is going to be difficult,” Zeigler said. NewsChannel 5 reported that more than 25,000 vehicles a day use the bridge, and that three other downtown bridges would still be open. Ed Branding, a real estate researcher, told the station, “It’s like putting eight gallons of traffic in about five gallons worth of bridges.”
The bid papers counted fewer cars and an earlier finish
TDOT’s January 2026 request for proposals for the same job, Progressive Design-Build contract PD2601, pin 136436.00, describes a different pair of numbers. It says the existing viaduct carries approximately 17,300 vehicles a day on average, 9 percent of them trucks. It calls for a prolonged full closure, demolition of that viaduct, and a rebuilt roadway from the Victory Memorial Bridge to Interstate Drive, just west of I-24. A project goal in that document is substantial completion no later than November 2028, and the schedule section anticipated construction starting in summer 2026 and finishing by November 2028. The department’s project page now lists construction beginning in the second quarter of 2027 and substantial completion in the third quarter of 2029. That later window matches the summer-to-summer closure Zeigler described. The page and the January proposal do not explain the gap between 17,300 and “more than 25,000.” This story does not pick a traffic count.
The proposal also shows why the utility work can stretch a closure. It requires moving or coordinating lines for Nashville Electric Service, Metro Water and Sewer, Piedmont Gas, TVA, AT&T, and several fiber companies, plus a regional stormwater trunk that has to be coordinated with CSX on the way to the Cumberland River. Zeigler’s point about lines going into the bridge is the public version of that list. The proposal’s instruction was to manage the closure so downtown stayed reachable. It did not draw the detour NewsChannel 5 says still does not exist.
What commuters can plan on, and what they cannot
Drivers can plan on a full closure measured in years, not weeks, aimed at the East Bank street grid rather than at a repair of the river span. They cannot yet plan a route. TDOT said it is announcing now so people have time, and it named the marathon as the point after which the closure starts. NewsChannel 5 said three other bridges into downtown would remain. It did not name them. The project page lists Zeigler as Region 3’s communications officer for the work, with Miller Bernhardt as the alternative-delivery manager. The photograph is an aerial from September 2026. The bridge in it is still open, and the approach has not been lowered.
Sources:
NewsChannel 5, Ben Hall, “Major bridge into downtown Nashville to close for two years beginning in Summer of 2027,” Nov. 12, 2026, https://www.newschannel5.com/news/newschannel-5-investigates/major-bridge-into-downtown-nashville-to-close-for-two-years-beginning-in-summer-of-2027
TDOT, James Robertson Parkway reconstruction, request for proposals PD2601, January 2026, https://www.tn.gov/content/dam/tn/tdot/alternative-delivery/progressive-design-build/pd2601/PD2601_James%20Robertson%20Parkway%20RFP.pdf
TDOT, Davidson County economic development enhancements, project page, https://www.tn.gov/tdot/projects/region-3/davidson-county-economic-development-enhancements--.html
Photo: King of Hearts, “Nashville from Cumberland River September 2026 003.jpg”, Wikimedia Commons, CC BY-SA 4.0, https://commons.wikimedia.org/wiki/File%3ANashville_from_Cumberland_River_September_2026_003.jpg