Oak Ridge cleanup crews can now check landfill wastewater tanks from their phones, DOE says
OAK RIDGE, Tenn. — Workers at the federal landfill that takes waste from the Oak Ridge Reservation cleanup can now watch wastewater tank levels and alarms from their phones, the U.S. Department of Energy’s Office of Environmental Management said Tuesday, Oct. 13.
The Oak Ridge Office of Environmental Management and its cleanup contractor, United Cleanup Oak Ridge, or UCOR, finished repairing water tanks and installing real-time remote monitoring at the Environmental Management Waste Management Facility, known as EMWMF, after more than a year of planning, preparation and field work, according to the department.
The landfill crew can now see the levels in all eight leachate tanks, the rate leachate is flowing in and any high-level alarms as they happen, DOE said. The system adds to an existing leachate control system that alerts crews to problems such as power outages.
Until now, crews had to report to the site to check tank levels, inflow rates and alarms, including during off-shift hours, holidays and weekends, according to the department. DOE said the data is protected by cybersecurity programs and only EMWMF superintendents and managers can see it.
“The installation of the remote monitoring equipment helps to ensure EMWMF remains compliant with operational requirements and continues to safeguard the surrounding environment,” EMWMF Federal Project Director Michael Vestal said in the DOE announcement.
The landfill also has four 240,000-gallon tanks for contact water, which is water that gets into the landfill and touches waste. When that water flows through waste and picks up certain materials, it becomes leachate. EMWMF manages up to 23 million gallons of contact water and up to 5.5 million gallons of leachate a year, DOE said.
Two of the contact water tanks were taken out of service, completely rebuilt and put back into use last year, and the other two recently had repairs to deal with rust on outside parts, according to the department. “These improvements to both our leachate and contact water management systems are especially beneficial during large rain events that can disrupt our routine operations,” UCOR Onsite Waste Disposition Manager Josh Pemberton said.
Sources:
U.S. Department of Energy, Office of Environmental Management, Ella Stewart, “Oak Ridge Innovation: Remote Monitoring Upgrades Strengthen Waste Management,” Oct. 13, 2026, https://www.energy.gov/em/articles/oak-ridge-innovation-remote-monitoring-upgrades-strengthen-waste-management
Photo: Lynn Freeny, U.S. Department of Energy (doe-oakridge on Flickr), “Truck hauling waste at the Environmental Management Waste Management Facility Oak Ridge,” 2004, Wikimedia Commons, public domain, cropped and color-corrected, https://commons.wikimedia.org/wiki/File:Truck_hauling_waste_at_the_Environmental_Management_Waste_Management_Facility_Oak_Ridge_(7204717346).jpg
More from Oak Ridge
All Oak Ridge newsNews · October 28, 2026
Oak Ridge now has about $15 billion in nuclear projects lined up, most of it private money, with about 10,000 jobs expected over five years
Federal energy officials pointed to Orano’s $5 billion enrichment plant, TRISO-X fuel, a Radiant microreactor line and Kairos Power, much of it on land that was once the K-25 complex. Here is what is coming, and why it matters beyond East Tennessee.
News · October 14, 2026
UT-Battelle leads nearly $5 million push for Oak Ridge Schools Innovation Center
A $2.5 million lead gift anchors founding-partner commitments for a PreK–12 innovation hub on the Oak Ridge High School campus.
News · October 14, 2026
Amentum opens its global nuclear headquarters in Oak Ridge
The Lafayette Drive hub has more than 150 experts, and a $500,000 scholarship program links Roane State and UT.
News · October 14, 2026
Water main replacement narrows traffic at South Illinois Avenue and ORAU Way for four weeks
Southbound ORAU Way is closed except for right turns. The city is replacing a leaking cast iron main.
News · October 15, 2026
Oak Ridge repaving moves through Bethel Valley Road this week, with four more streets up next
Roads stay open during milling, but drivers may see lane closures from 7 a.m. to 4 p.m. City Council has also moved its October work session to Monday, Oct. 26.